January 2018

  • technical part works fine (ETLRs, web, cat, eduroam db, monitoring, f-ticks)
  • ongoing requests resolved in timely manner
  • we have new member Albania / RASH
  • worked on GDPR
  • attended 1st GeGC meeting

December 2017

  • ftlr uptime 100%
  • we identified loop on etlr2 and rectified it (some lessons learned about  NAPTR records in DNS)

November 2017

...