  • Review the input document Work Items (Proposal)
    • discuss and agree on assumptions
    • discuss and agree on approach
    • clarif item characterisation
  • define next steps
    • distribute the tasks

Action items

  •  
ActionWhoDeadlineStatus
Set up bi-weeklies on Wed mornings, 10h-11h, starting 3 Jan 2024ChristophasapDone

Set up planning workshop and prepare a broken-down list of activities as input on 20 Dec, 9h-11h

Christoph (check with Marina)asapDone

Prepare a draft TOC for the report and check for project dependencies

Christoph (check with Marina)before 20 Decopen

apply for items in the list of activities, include your estimated efforts you're willing to contribute

allinput for 1st and 2nd bi-weekly in Jan '24not started

Backlog

  • Review existing services to identify opportunities and challenges to adopt the distributed technologies paradigm. Grab existing results as a start
  • Gather previous work done by the NRENs/universities on using SSI technologies, as well as other sectors. Croud-source among ourselves