This page contains information about roadmap for devops, but may include description to actual issues and developments.

RESPONSIBLE: Content is defined and maintained by devops team.

 

eduroam devops team is responsible for operating and managing operational side of eduroam. Devops roadmap notes any outstanding activities from the "business as usual". Business as usual implies:

  • technical part: maintain and when needed adjust configurations and resolve user reported problems for:
  • organisational part
    • provide content for www.eduroam.org + eduroam wiki
    • organise eduroam SG meetings
    • liaise with GeGC
    • liaise with JRA3
    • expert level support for user questions received

 

ActionDescriptionPriority (1-lowest, 5-highest)StatusDue DateAssigned toComment

NRO audit - first draft spec released

NRO audit is a new measure of evaluating the practices of
National Roaming Operators against the mandatory and
recommended requirements defined in the eduroam policy.

The aim is to gain knowledge of how well
NROs are aligned with eduroam policy.

The ones who are not following the mandatory requirements
will be urged to do so.

The ones who are not following the recommended requirements
will be advised and motivated to do that in greater measure.

 IN PROGRESSJan 2017  
NRO audit - final spec released NOT STARTEDMar 2017  
NRO audit - first audit run NOT STARTEDMay 2017  
NRO audit - audit report released NOT STARTEDJune 2017  
NRO audit - spec update released NOT STARTEDMar 2018  
NRO audit - second audit run NOT STARTEDMay 2018  
eduroam DB ver 2 - public draft spec releasededuroam DB ver 2 is revised version of database
that holds information about NROs, IdPs, Service Locations etc.




 FINISHEDJune 2016  
eduroam DB ver 2 - final spec released IN PROGRESSDec 2016  
eduroam DB ver 2 - SW released NOT STARTEDJan 2017  
eduroam DB ver 2 - uptake review NOT STARTEDMay 2017  
eduroam DB ver 2 - close ver 1.0 support NOT STARTEDJan 2018  

 

Examples for status codes:

NOT STARTED

FINISHED

IN PROGRESS

CANCELED

  • No labels