FoD Pilot 

Start Date:

Preparations for the pilot started in June 2017, the users are on-boarded to the pilot in October 2017.

End Date:

Expected end date for pilot is beginning of February 2018.

Pilot Description:

The pilot should test FoD version 1.5 especially its new features including:

The pilot will include security team in GÉANT Operations Centre and the following NRENs: RedIRIS, LITnet and EEnet. 


Pilot Category: Technology / Service 

This is a technology pilot, with its focus on the new features that are present in FoD v 1.5 and were not available in the current production version FoD v1.1.

Required Infrastructure:

The infrastructure that is needed for the pilot includes:

Pilot participants are welcome to contact JRA2 T6 team members: Evangelos Spatharas (evangelos.spatharas@geant.org) and David Schmitz (David.Schmitz@lrz.de) about the pilot.

David/Evangelos - please include names and e-mails of NRENs' representatives


Users:

FoD direct users are NOC and/or CERT engineers that implement the rules, and secondarily NRENs and any GÉANT project participating organisation.

Three NRENs participate in the pilot: RedIRIS, LITnet and EEnet.  

Objectives and means of verification:

The list of objectives, critical success factors and the means of its verification is provided in the attached xls sheet.

FoD 1.5. - KPIs_2017_09.xlsx

Communication plan:

The communication with pilot participants is currently organised directly between the two T6 participants and NRENs' representatives.