Name:
FoD Pilot
Preparations for the pilot started in June 2017, the users are on-boarded to the pilot in October 2017.
Expected end date for pilot is beginning of February 2018.
The pilot should test FoD version 1.5 especially its new features including:
The pilot will include security team in GÉANT Operations Centre and the following NRENs: RedIRIS, LITnet and EEnet.
Pilot Category: Technology / Service
This is a technology pilot, with its focus on the new features that are present in FoD v 1.5 and were not available in the current production version FoD v1.1.
The infrastructure that is needed for the pilot includes:
Pilot participants are welcome to contact JRA2 T6 team members: Evangelos Spatharas (evangelos.spatharas@geant.org) and David Schmitz (David.Schmitz@lrz.de) about the pilot.
David/Evangelos - please include names and e-mails of NRENs' representatives
FoD direct users are NOC and/or CERT engineers that implement the rules, and secondarily NRENs and any GÉANT project participating organisation.
Three NRENs participate in the pilot: RedIRIS, LITnet and EEnet.
The list of objectives, critical success factors and the means of its verification is provided in the attached xls sheet.
The communication with pilot participants is currently organised directly between the two T6 participants and NRENs' representatives.
David / Evangelos - can we organise regular meetings with pilot participants, e.g. once a week to speed it up? if so, please schedule the doodle and then update this part of the page