Scope, resource plan and timeline for deliverables for a detailed investigation to assess what layer 1 infrastructure is required if any and where for the future iteration of the GEANT network beyond 2020.
No. | Milestone name | Description | Expected (Month) | Task | Means of verification | ||||||||||||
1 | Layer 1 infrastructure study scoping | Scope, information gathering templates and NRENs communication plan developed for layer 1 infrastructure study | 3 | 1 Alexander Vandenhil | Internal Documents | ||||||||||||
2 | Layer 1 infrastructure study | Information gathered from NRENs | 6 | 1 Alexander Vandenhil | Internal Documents | ||||||||||||
3 | Layer 1 infrastructure study | Information analysed | 9 | 1 Alexander Vandenhil | Internal Documents | ||||||||||||
The above internal documents will provide input to the EC deliverables D5.2 and D5.6 "Revision of GÉANT Network Evolution Plan".