Plan

This section describes the plan to move the greenhouse concept forward.

 

Aim of this project: define a model to sustain the software developed by the GEANT association as a whole (including its members and/or associated peers worldwide).

 

greenhouse-plan

 

 

 

Activity NameDescriptionCommentStart MonthEnd MonthStatus
1. Concept Definition

Explore approaches to sustain software produced in the context of a collaboration where no model is already in place.

 

The idea of the Greenhouse has been discussed for a while.

Most of the background work has been done and it is available on this wiki space. See:

Differentiating the TERENA Greenhouse

 

Oct 2013Nov 2014DONE
2. InitiationGather requirements and the options to implement the greenhouse    
   2.1 Needs assessment

Document list of requirements for different products.

Assigned to: Nicole

Informal conversation with some of the project is ongoing for some time. See:

Product Needs Assessment

Output: Assess a select number of key products.

12 Jan 201520 Jan 2015NOT STARTED
   2.2 Gather info on models to implement the greenhouse

Short list of possible approaches  that matches the core requirements identified in 2.1.

Assigned to: Alessandra

 

 

Output: a matrix on the wiki with possible approaches.

See also:

Software Sustainability Within the TERENA Community

Differentiating the TERENA Greenhouse

2 Feb 201527 Feb 2015NOT STARTED
   2.3 Document to present the most suitable options

Prepare a document to present a short list of options and their risks/benefits.

Assigned to: Licia

Output: short document with recommendations on the approach to implement23 Feb 201531 March 2015NOT STARTED
3.  Select most suitable modelSelect the approach to implement. 31 March 201514 April 2015NOT STARTED
4. Execution

Implement the selected model.

Assigned to: TBD

 

TNC could be a good opportunity to gather some feedback if a proof-of-concept were available.

15 April 2015End JunNOT STARTED
      

 

 